Swapped concrete pumps mid-pour on a 4-story job in Phoenix

I had to make a call between two pump options last month. The first was a line pump that would have been cheaper but slower. The other was a boom pump that cost $2,800 more for the day. I went with the boom pump because we were pouring the 4th floor deck and the reach would save us 3 hours. It paid off. The pour finished at 2 PM instead of 6 PM, and we avoided overtime for the crew. That extra cost got eaten up by the schedule win. Has anyone else taken a hit on equipment cost to save time and had it work out better than expected?
1 comments

Log in to join the discussion

Log In
1 Comment
fox.skyler
Oh man, that's the kind of move where you hold your breath until it all shakes out! I love when a bigger upfront cost actually saves money in the long run (even if my wallet cried a little when I made the call). It's like when I splurge on a fancy shampoo for the shop - it costs more per bottle but the dogs come out softer faster and I get through the day without hating my life. You took a risk on that $2,800 and it sounds like it paid off big time. Beats the alternative of explaining to the crew why they're stuck until 8 PM pouring concrete in the dark.
4